Reference
B 109 Anklam bypass, demolition of buildings
Client: Straßenbauamt Neustrelitz
Time period: 2011 – 2012
Performance:
- 30.000 m³ uR Demolition of buildings as route clearing
- 30.000 m³ uR pollutant cleanup according to BGR 128, TRGS 519,521
- 1,200 t Disposal of construction waste with hazardous impurities
Special performance:
- 1,500 m³ demolish reinforced concrete foundations in the ground
- 580 m³ Demolish brick foundations in the ground
- 1,200 t Disposal of mixed construction and demolition waste with hazardous impurities
- 900 t disposal of soil with hazardous impurities
- 500 m³ disposal of asbestos-contaminated soil
- Pull 140 m piles of reinforced concrete
- 300 m piles from wood pull