BIOMASS COGENERATION PLANT – ELSTERWERDA

The Elsterwerda biomass cogeneration plant generates electrical energy and district heating for end customers from waste wood.

On the area of the district heating plant, the BMHKW was newly built and comprises, in addition to the silo plant, a boiler house, an attached operating and switchgear building, the machine house including steam turbine, an air condensation plant, a flue gas cleaning system with chimney and a delivery hall.

For scheduling reasons, the lower-lying basement of the adjoining machine house had to be built after completion of the ground level floor slab of the boiler house.

Typical power plant requirements regarding the positional accuracy of the anchoring elements for the plant components further complicated the work. 

Location: Elsterwerda/ Brandenburg

Client: mg engineering, Stadardkessel Lentjes

Executing company: ARIKON Hoch- und Ingenieurbau GmbH

Construction time: June 2003 to February 2004

Implementation: Single part performance of the shell

Construction volume: 2,4 Mio. €

Special features: Foundation of a lower basement following the completion of the ground slab of another building

 

Boiler house with adjoining operating building as well as the flue gas cleaning system including chimney with a height of 30 meters. 

 

 

 

 